1
|
- RADM Charles Hamilton, PEO Ships
10 January 2006
|
|
2
|
- CNO Priorities
- Navy Shipbuilding Plan
- DDG 1000 Program Status
- LCS Program Status
- LPD 17 Program Status
- LHA 6 Program Status
- T-AKE 1 Program Status
- Combatant Modernization
- Summary
|
|
3
|
- Sustain Combat Readiness
- Right combat capabilities – access, speed, agility, adaptability,
persistence, awareness and lethality – for the right cost
- Build a Fleet for the Future
- Balanced, rotational, forward deployed and surge capable
- Proper size and mix of capabilities
- empower enduring and emerging partners
- deter adversaries
- defeat enemies
- Develop 21st Century Leaders
- Through a transformed manpower, personnel, training and education
organization that better competes for the talent our country produces
and creates the conditions in which the full potential of every man and
woman in our Navy can be achieved
|
|
4
|
|
|
5
|
|
|
6
|
- Designated DDG 1000 ZUMWALT Class 07 April 2006
- Detail Design contracts awarded in August 2006 to NGSS and BIW
- Construction contracts to be awarded early 2007 to NGSS and BIW
- Mission System Equipment contacts to be awarded to Raytheon, BAE early
2007
|
|
7
|
|
|
8
|
|
|
9
|
|
|
10
|
|
|
11
|
- LCS 1 (LM) Under Construction
- Launched 23 September 2006
- Delivery Summer 2007
- LCS 2 (GD) Under Construction
- LCS 3 (LM) Contract Awarded June 2006
- LCS 4 (GD) Contract Awarded December 2006
- LCS Interface Control Document (ICD) Complete
- Both Open Architecture Combat Systems on Track
- Crews in place & Sailors in training
- First application of Sea Warrior principles
- PRE-COM crew members at shipyards supporting construction, at sea
training
and T&E
- Early Operational Assessment successfully completed for both designs
|
|
12
|
|
|
13
|
|
|
14
|
|
|
15
|
|
|
16
|
|
|
17
|
|
|
18
|
- Mission Package Computing Environment
- MPDL connectivity demonstrated between NSWC PC and LM/GD facilities –
Oct 2005
- MIW Software build 0.2 delivered and testing completed – May 2006
- MIW Software build 1.0 delivered and testing in progress – Sep 2006
- Mine Warfare Mission Package
- First Mine Warfare Mission Package Support Modules Delivered to NSWC PC
- Three support modules outfitted
- AQS-20A
- AMNS / ALMDS / AMNS
- RMS
- RMS cradle FAT and 200% load test
- Anti-Submarine Warfare Mission Package
- Sea Talon ACTD transitioned to POR
- USV Based Bi-Static sonar operations demonstrated in SOCAL
- MS OBS (Active Source)
- UTAS (Passive Array)
- Surface Warfare Mission Package
- NLOS-LS
- Successful PAM Seeker Captive flight test
- Successful BTV launch from motion simulator (Sea State 3)
- MK-46 Mod 01 30MM gun Structural Test Firing
|
|
19
|
|
|
20
|
- USS SAN ANTONIO (LPD 17)
- Delivered July 2006
- Commissioned January 2006
- PSA scheduled March 2007
- NEW ORLEANS (LPD 18)
- Delivered December 2006
- Commissioning March 2007
- MESA VERDE (LPD 19) – 91% complete
- GREEN BAY (LPD 20) – 74% complete
- NEW YORK (LPD 21) – 53% complete
- SAN DIEGO (LPD 22) – Keel lay 2007
- ANCHORAGE (LPD 23) – Start fab. 2007
- ARLINGTON (LPD 24) – Start fab. 2007
- SOMERSET (LPD 25) – Start fab. 2008
|
|
21
|
|
|
22
|
|
|
23
|
|
|
24
|
|
|
25
|
- Functionally replace LPD 4, LSD 36, LKA 113, and LST 1179 Ship classes
- Provide Increased
- Lift
- Survivability
- Mission Flexibility
- Service Life
- Improved Quality of Life
- Reduced Total Ownership Cost
|
|
26
|
|
|
27
|
- Replace LHA 1 class Amphibious Assault Ship
- Advanced Procurement funding for lead ship, FY07 (PB06)
- Milestone B approved January 2006
- Construction contract to NGSS anticipated in early FY07
|
|
28
|
|
|
29
|
- Requirements LHA LHD LHA 6
- Aviation (JSF) 0 19 23
- Aviation Maint (MV22) Limited Limited Full (2 MV22)
- Cargo (K cubic ft) 109 125 160
- Vehicle (K square ft) 25.4 20.9 11.6
- Troops 1,713 1,686 1,686
- Well Deck (LCAC) 1 3 0
- JP-5 (K gallons) 400 617 1,300
- Sustained Speed (kts) 22 22 22
- Service Life Allowance:
-
Disp None 2.5% >5%
- KG remains +0.5
ft >+1.0 ft
- Survivability (armor) None Limited Add’l
|
|
30
|
|
|
31
|
- T-AKE 1 USNS LEWIS AND CLARK
- Construction started September 2003
- Christened 21 May 2005
- Delivered June 2006
- OPEVAL completed December 2006
- T-AKE 2 USNS SACAGAWEA
- Christened 24 June 2006
- Builder’s Trials completed December 2006
- T-AKE 3 USNS ALAN SHEPARD
- Keel laid Feb 2006
- Christened Dec 2006
- T-AKE 4 USNS RICHARD E. BYRD
- T-AKE 5 USNS ROBERT E. PEARY
- T-AKE 6 – 9 under contract
- T-AKE 6 under construction
|
|
32
|
- Primary Mission: Provide Logistic Lift Capability as a Shuttle Ship from
sources of supply for transfer at sea to Station Ships and other Naval
Warfare Forces
- Ammunition
- Food
- Repair parts
- Expendable supplies and material
- Limited quantities of fuel
- Secondary Mission: Operate in concert with a T-AO 187 Class Ship (Fleet
Oiler) as a Substitute Station Ship to provide direct Logistics Support
to the ships within a Battle Group
- Description: Dry Cargo/Ammunition Ship
|
|
33
|
|
|
34
|
- 2006 Christenings:
- GRIDLEY (DDG 101)
- SAMPSON (DDG 102)
- 2006 Commissionings:
- USS FORREST SHERMAN (DDG 98)
- USS FARRAGUT (DDG 99)
- 2007 Christenings:
- STERETT (DDG 104)
- TRUXTUN (DDG 103)
- DEWEY (DDG 105)
- 2007 Commissionings:
- USS KIDD (DDG 100)
- USS GRIDLEY (DDG 101)
- USS SAMPSON (DDG 102)
- DDG 108 named
WAYNE E. MEYER
|
|
35
|
- Combat Systems
- Open Architecture Computing Environment
- CIWS Improvements
- IFF Improvements
- CIC Display Improvements
|
|
36
|
- CG Mod introduces critical new warfighting capabilities
- Enhances air dominance and C4I through numerous system improvements
(CEC, SPY and AEGIS Weapon System improvements, and Q-70 Consoles)
- Enhances gun weapon system capability (5”/62 Caliber Gun Mounts, Naval
Fires Upgrades: Optical Sight and MK160 Fire Control System)
- Improves force protection (ESSM, CIWS BLK IB, and SPQ-9B (ASMD))
- Provides COTS computing architecture as first step to Open Architecture
positioning CGs to more affordably receive future ballistic missile
defense, air defense and other upgrades
- CG Mod improves Operational Availability through reduced maintenance and
mission life extension
- Reduces combat system and computer program maintenance costs through
baseline commonality and consolidation
- Extends mission relevant service life to 35+ years (Combat Systems,
Smart Ship Upgrades, All Electric Alterations, LM2500 Digital Fuel
Control, Aviation Mods, Weight & Moment Improvements, Corrosion
Control, Quality of Life Improvements)
- Applies to CGs 52 – 73
|
|
37
|
- DDG Mod provides a comprehensive mid-life modernization strategy for the
DDG 51 class to ensure a mission-relevant service life of 35+ years
- Reduces manning and total ship class ownership costs via Hull,
Mechanical & Electrical technology upgrades (Full Integrated Bridge
Upgrade, Machinery and Damage Control Upgrades, Gigabit Ethernet DMS,
Wireless Communications, Digital Video Surveillance, Quality of Life
Upgrades, Advanced Galley)
- Provides COTS computing equipment in an Open Architecture positioning
DDGs to more affordably receive future ballistic missile defense, air
defense and other upgrades
- DDG Mod improves Operational Availability through reduced maintenance
and mission life extension
- Reduces combat system and computer program maintenance costs through
baseline commonality and consolidation
- Addresses obsolescence issues by retiring unsupportable systems
- Applies to DDGs 51 – 112 with a focus on earlier Flight I ships (DDG 51
– 71)
|
|
38
|
- Program Purpose:
- FFGs remain a principal shallow water asset
- Allow FFGs to meet mission requirements until last ship decoms in 2019
- HM&E portion of program addresses top Fleet FFG maintenance issues
- Provides 21 modernized ships by end of 2011
- Combat system modifications are limited
- Modernization Scope:
- PEO SHIPS
- (4) SSDG Engines
- (2) RO Distillers
- (1) COTS SLAD
- AFFF Bilge Sprinkler
- SSDG Fuel Return
- Vent Mods
- PEO IWS
|
|
39
|
- CNO’s Guidance:
- Sustain Fleet size via stable SCN funding
- Buy the right capability at the right cost
- Building the Right Ships
- DDG 1000, LCS 1, LPD 17, LHA 6, T-AKE 1
- Modernization and sustainment efforts extend service life, reduce
maintenance and total ship ownership costs and introduce new technology
to legacy ships
- A stable shipbuilding plan, coupled with affordability strategies, plus
a focused industry push for cost reduction, yield affordable platforms
|